![]() |
The Alternatives |
||||
|
The KCWMB Solution With the wetland mitigation bank option, Vandaly simply contacts KCWMB to determine if the apartment project is located within KCWMB's service area. If so, Vandaly must hire a wetlands consultant to assess the project's impact. Vandaly then presents the analysis to the Corps and TCEQ and obtains their approval to mitigate with wetlands from KCWMB. Vandaly purchases the requisite number of wetlands from KCWMB, thereby satisfying its wetland obligations. Vandaly avoids all the issues surrounding designing, building,
monitoring and maintaining its own wetlands mitigation project. Most importantly,
all of Vandaly's potential wetland liability issues are eliminated with the
purchase of the wetland credits. |
|
|
Traditional Off-site Mitigation With traditional off-site mitigation, Vandaly must build an off-site wetland in addition to developing the apartment site. The first step of a mitigation plan is site selection. This is not an easy task because the tract must have the correct soil characteristics to support wetlands as well as an adequate long-term natural water supply. After locating such a site, wetland experts, ecological consultants and civil engineers must be called in to formulate a wetland mitigation plan. The Corps and TCEQ, acting as the lead governmental agencies, must approve any wetland mitigation plan. Implementation of such a plan may commence only after the Corps and TNRCC have given their approval. Once construction has begun, invariably there are problems with contractors, delays and cost overruns because the creation of wetlands is highly sophisticated. Once the earthen work has been completed, it may take several years for the proper plants to take root, cover the area and create a wetland habitat. During this time the wetlands are under constant threat from invasion by upland plants or nonnative species, insufficient habitat development due to poor soil conditions, or even scant growth due to an inadequate long-term water supply. The Corps, TCEQ and other governmental agencies monitor the wetlands during this period in order to ensure that the mitigation site is, and will be, a fully functioning, self-sustainable wetland. Before the agencies sign off on the project, which may take three to five years, Vandaly is exposed to the potential liability of having to reconstruct the wetlands at the same or a more suitable site if they should fail. This liability is very real. Wetlands can only exist under the proper soil, water and plant conditions. Since Vandaly is attempting to convert an upland site into a wetland, it is essentially placing the new wetland in an area with a high risk of failure, thereby exposing itself to additional remediation costs should the wetland fail. |
|
Home |
KCWMB Overview |
Mitigation Banking |
Service Area |
Benefits |
Comparative Example |